Time and Work Problems Shortcuts and Tricks




About this tutorial:

Video duration: 15:28
Contribute towards Unacademy videos, because we are and always will be free and we need your help to continue making high quality videos: http://imojo.in/q9g7p

Check out Ravi Handa’s Online CAT Coaching course for CAT Preparation here: http://handakafunda.com/online-cat-coaching/

Solved examples on Time and Work dealing with ideas of proportionality, efficiency, pipes & cisterns, etc.

Follow us at http://facebook.com/unacademy

Post Author: OfficeTutes.com

Apple lover, ICT and LEAN consultant, MS Office lecturer My other website with video tutorials - Tutorials, guides and news for iPhones and iPads

50 thoughts on “Time and Work Problems Shortcuts and Tricks

    rahul yadav

    (August 4, 2017 - 10:10 pm)

    Three pipes A, B and C can fill a tank in 6 hours. After
    working it together for 2 hours, C is closed and A and B can
    fill the remaining part in 7 hours. The number of hours taken
    by C alone to fill the tank is

    rahul yadav

    (August 4, 2017 - 10:10 pm)

    A, B and C together can do a piece of work in 40 days. After
    working with B and C for 16 days, A leaves and then B and
    C complete the remaining work in 40 days more. A alone
    could do the work in

    Naga Durai

    (August 4, 2017 - 10:10 pm)

    nice class

    Priyansh Shrivastava

    (August 4, 2017 - 10:10 pm)

    Thnk u soo much sir

    PLZ ANSWER THIS IN BEST SHORT TRICK

    A, B AND C can do a work in 15, 20 and 30 days resp. They start the work together but after 4 days A leaves the work and after some more days B also leaves the work and rest work is done by C in 2 days. Then in how many days total work be finished ?

    smoked buns

    (August 4, 2017 - 10:10 pm)

    Thanks man, really needed a refresher on my algebra. Corelation got me hard on the first 2 exams and they were simple as hell.

    Puja Verma

    (August 4, 2017 - 10:10 pm)

    try to solve fast

    Marciano Nokip

    (August 4, 2017 - 10:10 pm)

    2. A work can be completed by 40 workers in 40 days. If 5 workers leave every 10 days, how many days work will be completed.

    ANSWER:

    Formula : A = 100 % / 40 days = 25 % every 10 days by 40 workers

    10 days = 25 % by 40 workers
    10 days = 21.87 % by 35 workers
    10 days = 18.75% by 30 workers
    10 days = 15.62 % by 25 workers
    10 days = 12.5% by 20 workers
    93.74 %

    100 % / 93.74% = 1.066 40 days + 10.66 = 50.66 Days

    Wanderlust

    (August 4, 2017 - 10:10 pm)

    Please provide the solution of this question–

    In village A, 12 men and 18 boys completed construction of a health center in 60 days, by working for 7.5 hours a day. Subsequently the residents of the neighbouring village B also decided to construct a health centre in their locality, which would be twice the size of the facility built in village A. If a man is able to perform the work equal to the same done by 2 boys, then how many boys will be required to help 21 men to complete the work in village B in 50 days, working 9 hours a day?

    (1) 45 boys

    (2) 48 boys

    (3) 40 boys

    (4) 42 boys

    (5) None of these/Cannot be determined

    INDI Monk

    (August 4, 2017 - 10:10 pm)

    Thank you nice way of presentation and if you don't mind what is the software used for this video

    RCMathsVideo

    (August 4, 2017 - 10:10 pm)

    very good

    Polighosh

    (August 4, 2017 - 10:10 pm)

    not helpful

    Nidhi Mittal

    (August 4, 2017 - 10:10 pm)

    Q. A and B can independently finish a piece of work in 25 and 20 days. They started working together after few days A left . after that B could finish the remaining work in 11 days. After how many days A left the work.
    kindly tell me solution to this question

    surya pi

    (August 4, 2017 - 10:10 pm)

    not efficient…

    vinay kumar choudhary

    (August 4, 2017 - 10:10 pm)

    Hi, how do you write during your presentation

    tyhf cghv

    (August 4, 2017 - 10:10 pm)

    Very poor teaching

    rajiv ranjan

    (August 4, 2017 - 10:10 pm)

    Q. A and B completed a work together in 5 days. Had A worked at twice the speed and B at half the speed, it would have taken them four days to complete the job. How much time would it take for A alone to do the work?

    nishant ranjan

    (August 4, 2017 - 10:10 pm)

    nice video sir

    Kriti Good

    (August 4, 2017 - 10:10 pm)

    finally came across a video which actually taught the type of questions that I was looking for..thanku so mch.

    Saurabh Soni

    (August 4, 2017 - 10:10 pm)

    Very good approach used to solve such problems.
    I am grateful to you 🙂

    RTR tr

    (August 4, 2017 - 10:10 pm)

    waste….

    MBS Baby Care AND Health

    (August 4, 2017 - 10:10 pm)

    good knowledge…nice session

    Pushplata Mallick

    (August 4, 2017 - 10:10 pm)

    Some persons were assigned a work to do in 26 days .They started the work
    but after 6 days, four persons were absent and remaining work was
    completed in 24 days. How many persons were assigned in beginning?
    1. 24
    2. 20
    3. 26
    4. 30
    6. Cannot be determined

    Mohammad Aman

    (August 4, 2017 - 10:10 pm)

    A does 20% less work than B. If A can complete a piece of work in 15/2 hours then B can do it in how many hours?
    How can solve this kind of problems

    piyush jain

    (August 4, 2017 - 10:10 pm)

    sir que no 6 ans is 36.90

    Sandip Sahoo

    (August 4, 2017 - 10:10 pm)

    Hi.gautam..i think and is 8.bcz B can do 1unit work so in remaining 3 days B can only 3 unit work so.18-3=15unit work can done by A+B.Bt in A+B do the work 3unit per day so A+B done the work together in 5 days.So Total days=5+3=8.

    P S

    (August 4, 2017 - 10:10 pm)

    Please provide the link to the concept video of TIME AND WORK .

    Chaitanya Yeturi

    (August 4, 2017 - 10:10 pm)

    What was the software you used to write .

    Abi Raja

    (August 4, 2017 - 10:10 pm)

    ur videos are very usefull fr even beginners sir..thnkx fr sharing:-))

    SURAJ GAONKAR

    (August 4, 2017 - 10:10 pm)

    @ravihanda… plz reply to the comments

    Rishubh Saxena

    (August 4, 2017 - 10:10 pm)

    sir can you make a playlist ??? please coz it is very difficult to watch the video in order as you said at the beginning  to watch the video on basic concept of time and work but i am unable to find that so if they are in order it will be quite helpful…thankyou  and at last i would like to thanxx for above awesome video…

    Asish Anatta

    (August 4, 2017 - 10:10 pm)

    Thanks man

    Gautam Malik

    (August 4, 2017 - 10:10 pm)

    Q4 it should be 12 days….they both start working together and can complete the work in 6 days. so in first 3 days they complete 1/2 of the work and then A leaves..so B will have to complete rest 1/2 of the work in 9 days so in total it takes 12 = (3 +9) days to complete.

    Ishi Chauhan

    (August 4, 2017 - 10:10 pm)

    I guess in question no 4 answer would be 12 days in total… please check and reply as I am already confused and this has made me more confuse.

    vishal singh

    (August 4, 2017 - 10:10 pm)

    answer for question 3 is 18 days not 8 days……

    kiran naik

    (August 4, 2017 - 10:10 pm)

    Sir i m learning the basics of mathematics now..please tell me how to solve with step by step example of 0.75/25*100
    i know the answer  is 0.03
    But please help me how to solve it without calculator..
    Thank you

    Vivek Verma

    (August 4, 2017 - 10:10 pm)

    thanks ravi…

    janani sns

    (August 4, 2017 - 10:10 pm)

    thanku for easy explanation sir. Can u pls solve this prob, " Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the same work in twenty-four days. Sixteen men and sixteen women started working and working for twelve days. How many more men are to be added to complete the remaining work in 2 day?"

    Rohan bhatt

    (August 4, 2017 - 10:10 pm)

    Hello ,

    I have one doubt in question 6 :
    Let the total work to be done is 630( LCM of A,B,C):
    the unit of work done by A in 1 min : 630/35 : 18 
    The unit of work done by B i :                        14
    The unit of work done by C                            21

    For 7 mins the work done will be 7*(18+14)/630 = 224/630

    The amount of work left is 1-224/630 = 406/630
    now the total time taken will be = (18+14-21)t/630=406/630
    t=406/11
    t= 37 days approx
    can you please tell me where my logic is wrong

    Sonia Sharma

    (August 4, 2017 - 10:10 pm)

    Thanks sir u are simply awesome

    suganya B

    (August 4, 2017 - 10:10 pm)

    till we get 72bd i understand in third problem.after that why u are dividing it by 3.5 b..can u pls explain it?

    AMREEN TAJ

    (August 4, 2017 - 10:10 pm)

    IN 2ND QUESTION U TOOK 60 DAYS…..BUT IT WAS ONLY 40DAYS OF WORK IN THE QUESTION???

    vinod yadav

    (August 4, 2017 - 10:10 pm)

    Excellent….awesome explanation

    Priya S

    (August 4, 2017 - 10:10 pm)

    good

    venya choudhary

    (August 4, 2017 - 10:10 pm)

    can i know y u took that x at the bottom of y in the first problem..
    Plzzzzz

    Jeric Tan

    (August 4, 2017 - 10:10 pm)

    I think #3 is wrong
    It should be 5B not 3.5B

    muthyam narsaiah

    (August 4, 2017 - 10:10 pm)

    good

    jogesh nanda

    (August 4, 2017 - 10:10 pm)

    Man u are brilliant…. Thanks for helping people…. really Appreciable…..

    Weloveroshni Fanclub

    (August 4, 2017 - 10:10 pm)

    great

    Kaushik Sadhu

    (August 4, 2017 - 10:10 pm)

    excellent tutorial! thanx a lot!

Leave a Reply

Your email address will not be published. Required fields are marked *