19 thoughts on “Microsoft Project Earned Value

    kartikey yadav

    (August 13, 2019 - 4:19 pm)

    very helpful, thank you so much

    Rob Hargroves

    (August 13, 2019 - 4:19 pm)

    Very helpful – thank you. Is there a way to generate a chart and transpose the EV data to a report, all in MS Project?

    Philip Richards

    (August 13, 2019 - 4:19 pm)

    Thanks for the excellent presentation. I'm just a little confused as to why the Paint Activity is showing a £160 BCWS before it is due to have started? Similarly the Lay Carpet shows a BCWS after the first update, even though it is not yet due to start?

    Patrick Brefo

    (August 13, 2019 - 4:19 pm)

    Sir, your program assume that your bcwp will always equal to acwp, how do you manually input ACWP? Assuming I spend more than planned? Please assist

    Meenakshi Lamba

    (August 13, 2019 - 4:19 pm)

    Good explaination

    Gabriel Espinosa

    (August 13, 2019 - 4:19 pm)

    Earned Value only works with recource type "Work" or does it work also with "COST"

    Danilo Safatle

    (August 13, 2019 - 4:19 pm)

    Very useful, thank you. I like it because it's fast and straight. Brazilians instructors go too slow and don't ever get to the point. Thanks again.

    Mostafa Abdel-Razek

    (August 13, 2019 - 4:19 pm)

    You talk too fast and it's not that useful. At day 1 in your project and before you advance the date, you had a planned valued on activity "Paint" why was that? Never explained. Fixed costs were entered at 75 pounds, yet actual cost only increased by 18.75 pounds. It was worth mentioning how you should actually enter actual cost for a task, not fixed cost! Not useful. I will have to be the firs one to give you "thumb down"

    Eduard Hernàndez

    (August 13, 2019 - 4:19 pm)

    There are also indicators based on CPI and SPI that predict the outcome of the project, also an existing field in MS Project

    Nabeel Ur Rehman

    (August 13, 2019 - 4:19 pm)

    very useful and crisp video. Thank you!

    Shabina Mushtaq

    (August 13, 2019 - 4:19 pm)

    Thanks for giving such example of earned value, it helped me to clear the concept more..

    Mangesh Gholkar

    (August 13, 2019 - 4:19 pm)

    Good one! Crisp and clear. Thanks.

    Roger Knowles

    (August 13, 2019 - 4:19 pm)

    Thanks. I review. I created them a while ago whilst I was teaching myself the concepts

    Oleksandr S

    (August 13, 2019 - 4:19 pm)

    at 4:55 you say that "you are ahead of yourself". Doesn't an SPI less than 1 mean that your plan is actually behind schedule? 🙂
    Take a look, the earned value there is two times less than planned value. Best of luck.

    Roger Knowles

    (August 13, 2019 - 4:19 pm)

    Stephan SPI is at 0.88 as the whole project is not complete. Think of it like % complete. if I was perfectly on track it would be 1, at the moment it is 88% there is still an outstanding task.

    Stefan Badescu

    (August 13, 2019 - 4:19 pm)

    How come that at min 6:02 when the first and the second task are completed, the SPI is 0,88, even though the project is much ahead, not behind?

    Martin Karuiru

    (August 13, 2019 - 4:19 pm)

    Excellent

    Kristen Scipio

    (August 13, 2019 - 4:19 pm)

    Amazing! Wish I found this video weeks ago! But better late than never…Thank you sooo much!!!

    ezgiezgi8

    (August 13, 2019 - 4:19 pm)

    This was an amazing video. Thank you so much!

Leave a Reply

Your email address will not be published. Required fields are marked *